Prev: Aug 2006
back
Next: Oct 2006
September 5 - The double car garage area is filled and packed.
September 5 - Center piers are completed and ground is leveled in preparation for pouring crawl space slab.
September 11 - Trusses for the first floor arrive.
September 11 - The crawl space slab is poured.
September 14 - Rains have come.
September 20 - Trusses are being placed. The open area on the front is the front porch.
September 22 - Trusses are in place and ready for subflooring.
September 25 - The first floor subflooring is finished.