July 1 - Once the drywall is finished then the walls and ceilings will be primed and ready for trim.
July 1 - The first two coats of drywall mud are on. The drywall will be finished in a few days.
July 8 - After the walls and ceilings are primed in the trim will begin.
July 8 - The tiling around the tub is coming along nicely.
July 8 - The drywall is all sanded now and ready for paint.
July 12 - The walls and ceilings are all primed in now and ready for interior trim.
July 12 - The tile around the tub is finished now and looks really good.
July 23 - The doors have plinth blocks to transition from the baseboard to the casing just like the rest of the house.
July 23 - Interior trim started today and is coming along nicely.
July 23 - The window in the sitting area is all trimmed out.
July 25 - The sitting room attic access door is finished. A cabinet will be built on the left wall here.
July 25 - The interior trim is nearly finished now. The window seat is finished and the window needs one more piece of moulding.
July 25 - The wainscot in the bathroom is finished now.
July 25 - The wainscot in the bathroom is finished now.