June 1 - Plumbing rough in has been completed. Soon electrical and HVAC (air conditioning) will be done.
June 1 - Siding is being installed. The exterior trim is finished.
June 5 - The air conditioning rough in was finished yesterday. Siding and exterior trim continues.
June 7 - Siding continues to be installed. This morning the vent (at the top) was built and will be installed.
June 12 - Siding is near completion. The deck needs to be built and the final pieces of siding will be installed.
June 12 - The vent is built and installed. The deck on the right side will have a post in the corner for support.
June 13 - This is Gitlitz Garage from the road. The siding and trim are on, but not painted. The fence in front will come down as soon as construction is complete.
June 15 - Gitlitz Garage is taking shape. This is taken from the front porch at Gitlitz Cottage.
June 18 - The garage roof does not show up well because it is still the black ice and water shield. This week, steel roofing (like the cottage) will be installed.
June 18 - The front view of Gitlitz Cottage and Garage.
June 20 - The roof at Gitlitz Garage is finished. The deck still needs to be built.
June 20 - This is a view of the garage from the house. The dark triangle in the upper right corner is the front porch roof of the Cottage.
June 21 - This is the Garage from the temporary entrance. The small room at the right is a storage room.
June 21 - This a view from the lake side. The right door goes up the stairs to the upper office. The door on the right goes into the garage.