Lightcap Residence: October 2022
Prev: Sep 2022
back
Next: Nov 2022
04 October 2022 - Framing materials are on site. Work should begin soon.
11 October 2022 - Framing the first floor has begun. Notice the steel cables holding the steel plumb during the framing process.
11 October 2022 - Bracing cables are visible here also. The engineered lumber beams are resting on sill plates (placed on the block piers and walls).
11 October 2022 - From a slightly higher elevation, a number of floor joists are visible.
11 October 2022 - The porches have engineered beams for support.
11 October 2022 - A lot of framing material is on site ready for installation.
18 October 2022 - The building supply truck just unloaded his materials.
18 October 2022 - Framers are putting down the subfloor. Looking towards garage.
18 October 2022 - More subfloor is down. Looking towards guest house.
18 October 2022 - The new materials are being covered for protection in case it rains.
25 October 2022 - Wall framing of the first floor has begun.
25 October 2022 - Sill plates (2x treated lumber) has been placed over the block stem walls in preparation for framing the garage.
25 October 2022 - Notice the sill plates between the blocks and the framing.
25 October 2022 - The outer walls are being framed. The framers started on the land side and are working their way to the water side of the house.
25 October 2022 - The house is a good way off the ground. There will be hog fencing installed as exterior trim is being done.