August 24 - The forms are in place. Plastic is down. Steel is in the footers. Tomorrow, we pour.
August 24 - Plumbing pipes are in place The large pipe is for the toilet. If you look closely, you will see the two pieces of 5/8 inch steel rebar in the footers.
August 25 - We poured the foundation on Wednesday. It took about 18 yards (36 tons) of concrete.
August 27 - Friday, the forms were removed and framing lumber was delivered.
August 30 - Monday, the bottom plates were installed and bolted down.