June 18 - Most of the trenches for footers were dug on Wednesday. One wall was not excavated enough, so it has to be hand dug. On Friday, the plumber will install a sleeve in the footer trench to run plumbing to the basement. Steel will be placed this week. The footers should be poured mid next week, weather permitting.