Prev: Aug 2007
back
Next: Oct 2007
September 6 - The garage has hurricane fabric for each window and door. The fabric will be labeled and stored in bags.
September 12 - Interior doors have been installed and trimmed out. Baseboards and other interior trim is being done.
September 12 - Interior painting is being completed. There is wainscot around the bottom of the room.
September 13 - The garage downstairs has been painted. It needs trim between the simulated T-111 and sheetrock.
September 13 - There is a nice storage area under the stairway. The box on the right is the breaker box. Right now, it is masked for painting.
September 13 - Upstairs, the windows are painted. Chair rail is being installed between the sheet rock and wainscot. The walls have their first coat of paint.
September 14 - Trim between the 'T-111' and sheet rock has been installed in the garage bay.
September 14 - Baseboards and chair rail are finished in the main room. Baseboard is needed in the bathroom. The walls have their first coat of paint.
September 19 - The storage room (under the deck) is trimmed. It has the concrete board 'T-111' on the lower walls.
September 19 - The finished stairs are being installed.
September 26 - The deck is being built over the waterproof coating. It will also have railings, of course.
September 26 - The divider is being trimmed. Wood trim has been installed around the stair well. Final painting is being done. The floor will have carpet.
September 26 - Downstairs has its final paint. The garage door will be installed early next week.