04 April 2023 - The block walls are all topped out with ledger blocks now except for the porches.
04 April 2023 - The walls will be poured with concrete next, then the dirt back-filled and plumbing installed.
04 April 2023 - The garage footprint is laid out. It will be formed and poured soon.
25 April 2023 - Trenches are dug for the footers and the dirt leveled for the garage.
25 April 2023 - Trenches are dug for the footers and the dirt leveled for the garage.
18 April 2023 - The garage slab and walkway are being formed for concrete.
18 April 2023 - The fill dirt will be spread and packed. Then a vapor barrier and steel will be laid, then inspected and then concrete poured.