Padron Residence: April 2023
Prev: Mar 2023
back
Next: May 2023
04 April 2023 - A bench is being built in the mud room.
04 April 2023 - Cabinets are in the master bath ready for installation.
04 April 2023 - Most of the exterior of the “stables” is finished and ready for painting.
04 April 2023 - The roof of the great room in the “stable” has spray in foam insulation.
04 April 2023 - The roof of the great room in the “stable” has spray in foam insulation.
04 April 2023 - Kitchen cabinets are being installed.
04 April 2023 - The front doors are in place. They are still protected with plywood on the exterior side.
11 April 2023 - An opening for a new door has been cut into the wall of the VIP room.
11 April 2023 - The main house porch ceiling is about finished except for beams.
11 April 2023 - Kitchen perimeter cabinets are installed and the island will be next.
11 April 2023 - More cabinets are on the left side of the kitchen and in the pantry.
11 April 2023 - The entrance foyer is dramatic.
11 April 2023 - A trim carpenter is working on the master closet built-ins.
11 April 2023 - This closet is finished and ready for paint.
18 April 2023 - The interior stairs are nearly complete.
18 April 2023 - The master bedroom morning bar cabinets are installed.
18 April 2023 - This master closet if ready to be painted.
18 April 2023 - The kitchen has a lot of cabinets and will be beautiful when done!
18 April 2023 - Cabinets are being placed and installed in the kitchen.
18 April 2023 - Cabinets are masked in preparation for interior paint.
18 April 2023 - Insulation is installed in the “stable” Billiard room.
18 April 2023 - Trim materials are staged in the “stable” Billiard room.
18 April 2023 - The exterior siding and trim has been caulked in preparation for paint.
25 April 2023 - Most of the exterior of the “stable” (left) is complete and awaiting paint.
25 April 2023 - The large floor sanding machine will make many passes to get the floor sanded down.
25 April 2023 - The master closet flooring is being sanded for finishing.
25 April 2023 - The flooring is being finished around the cabinets in the kitchen.
25 April 2023 - This is the foyer floor. The dark spots are patches to fill cracks and large voids.
25 April 2023 - Techs are scraping the reclaimed wood floors in the main house in preparation for finishing.
25 April 2023 - The ceiling of the billiard room is being finished. The beams will be trimmed soon.
25 April 2023 - The “stable” condensing units are being tied into the inside units. They will be started up next.