Padron Residence: March 2023
Prev: Feb 2023
back
Next: Apr 2023
07 March 2023 - The carpentry on the outside of the main house is nearly complete.
07 March 2023 - The chimney end of the “stable” now has wood siding installed.
07 March 2023 - The screened porch ceiling is installed. The beams will be trimmed next.
07 March 2023 - Beams in the kitchen have been wrapped with wood and are impressive!
07 March 2023 - Samples colors of paint have been applied to a few of the great room beams.
07 March 2023 - The interior trim of the great room is nearly complete.
07 March 2023 - The master shower tile is in progress.
07 March 2023 - The tile in the upstairs shower in the main house is complete.
07 March 2023 - The tile work on the floor is exceptionally well done.
07 March 2023 - Reclaimed wood flooring is installed in the upstairs bedroom.
07 March 2023 - Metal roofing is all complete now on the main house.
07 March 2023 - Metal roofing is all complete now on the main house.
07 March 2023 - The standing seam roof has been installed on the “stable.”
14 March 2023 - Exterior siding is being finished up on the “stable.”
14 March 2023 - The front gable of the main house is nearly complete.
14 March 2023 - Interior trim carpenters are working on the kitchen ceiling boards.
14 March 2023 - Some cabinets are on site.
14 March 2023 - The great room is great indeed. It is spacious and looks nice with the large windows and beams.
14 March 2023 - A generator has been placed on the pad behind the “stable.”
21 March 2023 - Carpenters are working on the front porch trim.
21 March 2023 - The screened porch ceiling boards are done. Beams will be finished up next.
21 March 2023 - The kitchen ceiling boards are being installed. The black squares are can lights. Thes have a small aperture which has to be routed into the ceiling boards.
21 March 2023 - The master shower floor tile has been laid.
21 March 2023 - The back hallway tile is down and now has protective coverings over it.
21 March 2023 - Exterior trim on the “stable” is nearly complete.
21 March 2023 - HVAC ducting in the “stable” great room is in place. AC rough in work is continuing in other rooms.
21 March 2023 - The equipment room has an air handler for the HVAC. The blue wire bundles are for A/V equipment.
21 March 2023 - This is another view of the equipment room. A technician is working near the air handler.
21 March 2023 - Exterior trim and siding are mostly complete. Paint will begin before long.
28 March 2023 - The generator at the “stable” is wired. Gas has not been connected yet, but is close by. The gas regulator is the blue-green device at the edge of the pad.
28 March 2023 - Air conditioning condensing units are in place at the “stable.”
28 March 2023 - The west wall of the “stable” has siding. It has been caulked and will be painted soon.
28 March 2023 - Beams and the ceiling of the porch of the main house have been trimmed.
28 March 2023 - More of the kitchen ceiling is installed. The small openings are for can light lenses.
28 March 2023 - The other half of the kitchen ceiling is being installed.
28 March 2023 - The great room trim is complete around the windows and on the beams.
28 March 2023 - A carpenter is finishing the trim in the master bathroom.
28 March 2023 - The side porch near the garage has siding. The exterior is almost ready for paint.
28 March 2023 - The front gable of the main house is now complete and ready for paint.