Prev: Jan 2012
back
Next: Mar 2012
February 7 - The roof is complete on the carport.
February 7 - The exterior trim is on the storage building. Painting has begun and once it is complete, we will put the cedar siding on it. Paint will be applied to all of the trim for protection.
February 7 - The carport trim is finished. The columns are wrapped. The ceiling is trimmed like the porches and walkways. The columns are primed, but not painted yet.
February 7 - Yesterday, we began installing the interior plywood on the walls of the storage building. This is the back wall. We will put some small trim boards around the air conditioner.
February 7 - The roof is on the storage building. All roofing is in place on both additions.
February 8 - The walkway to the storage building is built. We curved it so it is easy to access either from the house or playroom. You can see the air conditioner (for dehumidification) in the storage room.
February 8 - The carport painting is completed. The can lights are installed. The motion light (which shines down the walk and into the parking area as well as the carport) is installed.
February 8 - The air conditioner exterior trim on the storage room is installed and painted. The wall will receive cedar shingles to match the house and apartment.
February 8 - This is a view of the motion light. The light shines down the walkway (and spills into the parking area). The other light illuminates the carport area.
February 8 - The rear porch ceilings are painted haint blue.
February 8 - The interior of the storage building is finished. Lights are installed. Only the air conditioner and door are trimmed. We did not install baseboard, crown or any other trim since it is a storage building.
February 13 - The trim in the game room is gray.
February 13 - There are three sets of chrome shelves in the storage building.
February 13 - There are black shelves is in the game room.
February 13 - The storage room floor is gray with black and white chips in it. The chips also make the floor less slippery.
February 13 - The gas grill is on the back porch.
February 13 - The siding looks good on the storage building. The door has been painted the exterior tan color.
February 13 - You can see the storage building on the left edge. The dumpster will be pulled soon.
February 15 - The storage building.
February 15 - The shoe moulding is down, caulked and painted.
February 15 - This is a view of the storage building from the apartment balcony. Of course, the ladder and walk board will be removed.