December 5 - Footers are being dug around the guest house slab. The box just past the large white pipe is for the bath tub connection. We have a good deal of rain forecast for the next three days, so the footers will have to be touched up before we pour. We will also have a soil compaction test, treat for termites and lay poly and steel before we pour. We had hoped to pour this week, but the weather may not allow this.