January 2 - With it 20 degrees outside we placed two propane heaters to warm the house so tile and wood floors can be installed. Bottles for smaller room heaters are lined up on the wall.

January 10 - More progress has been made on the great room ceiling. This will get a white wash finish.

January 10 - The decorative tiles are in place and the tile is nearly complete in the master shower.

January 10 - The decorative tiles are in place and the tile is nearly complete in the master shower.

January 17 - Some trim is installed around the great room dormers but we don't like it. It will be changed out.

January 19 - The dining room ceiling boards are installed. The face of the beam will receive a paneled detail.

January 19 - The master bedroom ceiling boards are installed. The center beam will be trimmed out soon.

January 19 - These are the dresser and bench seat in the master dressing room. They will get wooden tops.

January 26 - One window is trimmed in the breakfast room. The outlet in the corner has to be moved in order to trim the others.

January 26 - There is still a good bit of trim left to do around the dining area. The cabinets were installed so the counters could be templated.