This carriage house includes a two bay garage, utility areas and an upstairs two bedroom apartment.
From Start of Slab to C. O. was 136 calendar days or 19 weeks, 3 days or 4 months, 2 weeks, or 91 work days.
From Building Permit to C.O. was 23 weeks, 2 days. Building Permit: February 12, 2013 Start of Slab: March 11, 2013 Final Inspection (C.O.): July 25, 2013